The NT Environment Protection Authority determined the project requires assessment at the highest level under the territory's Environment Protection Act, the first proposal of its kind to reach that tier, citing ten environmental factors and a "low level of confidence" in the effectiveness of Energy North's proposed management measures (NT EPA, 2026; ABC News, 2026). The project would extract up to 4 billion litres of groundwater annually and build a 191-square-kilometre campus including gas turbines, a solar farm, an airstrip, and accommodation for 4,300 construction workers (ABC News, 2026).
Energy North vice-president Daniel Hunter described the 2028 date as indicative and said the company would confirm new timing once the regulator sets terms for an environmental impact statement. He said the project agreed with the regulator's reasoning and that detailed management plans were exactly what the EIS process is designed to produce (ABC News, 2026).
The delay sits within a broader pattern. NextDC pushed back a Melbourne expansion over energy supply concerns, and Goodman withdrew a Sydney project after resident opposition (Reuters, 2026). Beetaloo Energy has proposed a data centre near Darwin twice the size of Project Ares, which would consume up to 400 terajoules of gas per day (Economic Times Data Centers, 2026). The Northern Land Council told a federal inquiry that expedited Aboriginal consultation "does not produce prompt consent" (Reuters, 2026).
BuiltWorld AI Operational Take: The regulator's decision to wait for federal policy is the signal that matters. Australia's planning frameworks were written for projects a fraction of this scale, and a 1-gigawatt campus on pastoral land tests assumptions about water extraction, sacred site protection, and on-site generation that no previous referral has addressed. Developers should treat the federal AI standards expected in 2027 as the real gating milestone, not the local EIS timeline. Any schedule built before those rules are legislated carries a policy risk that no amount of early engineering can retire.